Installation of a 1,486 mm diameter steel casing
Length of 165 m completed in one pull
The choice of tunnel boring machine is specifically based on the conditions of the rock in place. An exhaustive geotechnical campaign was conducted for this project. The following field and laboratory tests were performed:
Following the analysis of the geotechnical data, several tunnel boring techniques were considered, and the microtunneling technique proved to be optimal.
Design calculations were specifically executed for the microtunneling technique according to industry standards.